| Other Projects: Vortex 3-wheel Vehicle 17' Wind Turbine Solar panels/tracker Bradly GT II Kit Car 1966 Ford Fairlane GT Spinning Wheels Xantrex XW Monitoring/Logging Software |
Search this site: |
Tower
This page shows tower and tower modifications that I performed for this project
|
Everyone that know much about wind power typically says that the higher up you put the turbine the better the outcome, primarily due to turbulence and ground drag, putting up higher puts it into a more laminar/smoother flow of air. Initially I was interested in putting up a 50' (even knowing that I would loose some output) or so tower but in the end went with the decision that an 80' tower would be best. In addition I do not want to put a guyed tower as I think that the guy wires are ugly and I also did not want to deal with them. I am probably putting up a free-standing lattice tower or a monopole design. I am leaning towards the lattice as I will be able to hinge the base and raise/lower it or have the option to climb it for maintenance. |
||
| Tonight I looked at the framework structure and components that I need to make for the turbine, in an effort to attempt to calculate what the final total weight might be.
So I went back to the 20' and 17' websites to do comparisons. The framework for the 20' was beefed up considerably over the 17' turbine that they made and it weighs in at about 400lbs, while the 17' one weighs in at 160lbs. In addition I saw some notes that mentioned that they had to do a couple of repair jobs on the 17' after it was put up. In quickly looking at basically how I wanted to build the unit (pretty beefy), I calculated that my turbine would come in at about 300-350lbs total. |
||
| It's been a while since I have posted to this website I have been busy with other projects, however all parts have been received and are awaiting some spare time to begin work on the turbine.
In the mean time I have been researching towers and recently I was referred to a tower company that manufactures and installs towers AN Wireless. Typically the towers that they sell are for communications equipment and not for wind turbines. They are fairly close and just over the border in Somerset county PA. After talking to Dan Simmonds for a while and filling him in on the details of my project he decided that to ensure that there would not be any problems that I would need to pay $550 for an engineering study. For this their engineers will decide if their current series of towers were suitable, if not then they would propose a design for my application. At first I balked at the cost, then realized that it would be money well spent so I agreed and sent them out a check. He stated recently that they did mount a Skystream 3.7 generator (12' blade diameter) on top of a 100' HD series tower that they make, however the 17' diameter might exceed the capacity. The price for a 70' freestanding HD series tower seemed quite reasonable at just over $3100. One side note is that none of their towers are tiltable, meaning that either a crane is used for raising/lowering the tower or a davit be constructed for raising/lowering the wind turbine. Dan had also mentioned that there was a 3 month wait for towers, as this is their busy period. I figure that the timing would be just about right for me to build the turbine and make the tower base which puts the installation into September, so I had him put my name in the queue. Here are a list of my requirements:
|
||
| I got an email from the tower engineer that did the engineering study for AN Wireless and it appears that using their HD 70' tower with a 10' long 4" diameter schedule 40 top stub is no problem, no modifications or special tower construction is necessary for my 17' diameter wind turbine.
In addition they specified using their A style pad/pier foundation (which they show here), so it would appear that their towers are plenty strong enough and the weak link would be the foundation. In the drawing it is not really clear how the rebar structure should be built, however there are pictures of an actual foundation construction which clarifies this issue. I plan on starting to dig out the foundation in a couple of weeks and get started on building the rebar structure and pour cement by the end of July. It is recommended that the cement cure for 30 days which puts me almost into September. This time frame works out almost perfectly as AN Wireless said that I can expect delivery of the tower that month. |
||
| I talked with a local tower erection crew and we scheduled his crew and a crane to erect and place the tower the first week in October. Their prices were quite reasonable, They mentioned that the crew gets a hourly rate and the crane service should be under $1000 so I gave them the job. I had talked with another company about tower erection, however they would have come from a LOT further distance, and typically you get charged for travel as well. |
||
| AN Wireless had a break in their work schedule and tomorrow I am going to their location to pick up my tower!
Their location is less than an hour from my house so I will be picking it up myself and saving a bunch of money instead of having the tower shipped to me by truck! During this week they preassembled each individual section so that I do not have to assemble them (nice). I will be using my car trailer to haul it back home. The combined weight of the seven tower sections weigh about 1,600 lbs and my trailer has a capacity of 7,000 lbs so weight should not be a problem. Here is the breakdown of the tower costs:
|
||
| I picked up my tower today, as long as I had the trailer I also purchased all of the re-bar that I need for the foundation reinforcement.
Some of the sections are small enough that they could go inside other sections making it stack better. In the plastic tubs are an assortment of nuts/bolts/etc for assembling the tower sections, including the 3/8" diameter life-line, dual grounding kit and the mounting brackets for the top stub. Here is a picture of the tower loaded onto the trailer:![]() |
||
| Finally got around to digging out the hole for the tower foundation. It is basically 9' x 9' square and 6' deep, it basically took all day using the back hoe on my tractor.
Out here there is very little 'flat' land, it is all mountain or hill side so the top side of the hole was almost a foot deeper than the bottom. Here is a picture of my prize tractor, it's not real big but just about the right size. I don't know what I would do without it now days, I have a bunch of attachments for it, brush hog, post pounder, back hoe and front end 60" snow blower for the winters. |
||
| Got out my plasma torch, cutting saw and welder. I got all of the rebar cut up into the specified lengths, bent into shape and then welded the sections up. This job also took the better part of a day to complete.
I did not have to weld up the rebar, but I feel that it makes installation a whole lot easier than trying to hold everything together with wire. The final assembly will be done using wire however as it would be too difficult to completely weld up all the rebar the assembly would be too heavy and awkward to move - easily that is. There are two rebar assemblies that get put into the bottom of the hole and are about 8' 6" square, I did weld up a bunch of 'feet' on the bottom piece to help space it up off the bottom of the hole. |
||
| I got into the pit to clean out around the bottom edge and to level off the bottom. Even though I have a back hoe, this has to be done by hand, or at least I am not good enough from up above to do this using the backhoe.
I was able to get all the rebar into the pit and wired up, this took a while as I was working alone and the large 8' 6" sections of welded up rebar turned out to be quite a handful. I cut up about 12 lengths of 12" long rebar to separate out the two large rebar layers. By the end of the day I got the 4 sections of the center pedestal rebar in place, along with the 5' long tower section all in, wired up and basically sitting on top of the large bottom layer of rebar. I forgot to take a picture of the rebar, but here is an image from the AN Wireless website that shows the large rebar pad on the bottom with the columnar pier rebar and the tower base in the center section of the pit. One thing that is missing is additional diagonal braces on the tower base that tends to get in the way of the rebar: |
||
| The other day I purchased about 20 - 10' long 2x4's, 6 - 10' long 2x6's, 4 - sheets of 3/4" plywood, 200' of 1-1/2" conduit and 6 - 1-1/2" conduit 90 degree elbows. The tower is located about 90' away from my garage and I wanted to run two lengths of conduit from there out to the tower, one run will be used for power and the other for data and control lines.
Again working alone I cut up the 3/4" plywood into 4 pieces of 42" x 70" long sections and put three lengths of 2x4's horizontally, one across the top, bottom and middle. Two of the sections had the 2x4's cut 3" longer so that they overlapped the other section and could tie them together. I lowered all four of the sections into the pit and temporarily rested it on top of the bottom rebar platform, the wire ties held up fine (this was a concern.) Once in place I screwed all four sections of the plywood together with essentially about 2# of 2" long screws. Along the top outside lengths of two of the sections I screwed 2 lengths of 2x6's which extended out from the form by about 5'. The ends of these lengths were used to lift the entire plywood form assembly up off the rebar by about 4" and leveled off on the ground using cinder blocks, wood blocks, whatever so that the entire top of the form was level in all directions. It was also centered around the central rebar so that each inside of the form was about 4-5" away from the rebar. I also had to dig out the uphill section where the form supports extended into, and on the downhill side block them up. I ended up digging out almost 18" on the uphill side: |
||
| I spent most of the morning digging the trench from the garage out to the tower using my back hoe, laying the two runs of conduit and back-filling the trench in. I ended up cutting some 2-1/2" holes using a hole saw so that the two runs of conduit would be embedded into the concrete form and come up on the inside of one of the tower sides. With the conduit ran towards the inside of the tower it should help keeping it from getting damaged.
I needed to lift slightly the tower section so that it would be the proper height above the finished level of the form, so I used some rebar to make up a small A-Frame. Here is the A-Frame that I quickly made up out of some rebar: I used this A-Frame along with a come-along to lift each leg of the tower section and then using a C-clamp I clamped it onto a 2x6 that rested on the top of the form. This not only lifted the 5' tower section but also the central rebar assembly, in all probably about 200# total. Once the tower base was in place I spent the rest of the afternoon providing side support all around the form so that when the concrete was poured it would not 'blow out' the form. There is tremendous forces with the amount of concrete that is required for the foundation, at a minimum of 9 cubic yards of concrete! My good friend Paul Schreiner stopped by to help out and we ended up putting vertical braces along the outside of the form and on each side six horizontal braces to the inside of the pit. These horizontal braces will ensure that the sides of the form do not 'blow out'. |
||
| 12 yds of 4000 psi concrete
(that's about 24 TONS of weight)
Paul Schreiner (my best friend and a former concrete guy) came by to help out with the concrete pour today and brought over his arsenal of concrete tools, most importantly a concrete vibrator! This vibrator is used to ensure that there are no air pockets trapped in the concrete and that it is a single solid mass. Prior to the concrete truck arriving I double checked that the tower base inside the form was level and that each leg was at the proper width. I ended up making some minor tweaks as once the concrete is poured this can not be adjusted. An 1/8" error at the base for level can turn out to be a foot at the top of an 80' tower so it is best to get it as close as you can before you pour the concrete! We ended up using almost 12 cubic yards of concrete! Initially I had ordered up 10 yards but we ended up a little short, they had to make a second trip with the final 2 yards to finish off the job. One important side note is that with my climbing around on the top of the suspended form yesterday, it 'tweaked' the horizontal supports and one corner ended up being about 1" too high. During the short break between the first concrete delivery and the second we tacked on some boards along two sides and marked out a level top plumb line in which to finish off the concrete. The concrete truck made *huge* divots into the pasture that I had to fill with dirt after the job was done. Lastly, prior to the concrete setting I put down about 1 gallon of sealer onto the top of the wet concrete. We used this method on my driveway and I liked the results. Here are a couple of pictures showing the completed pad/pier foundation from a couple of angles so that you can see the conduit entering the form and the location on the inside of the tower base where they come out. I put a piece of rebar between the two sections of the tower base so that the conduit stayed towards the inside of the tower, this was to merely hold them in place and will be removed once the concrete sets: |
||
| Today I decided to turn my attention to the top of the tower. I had some 3/8" triangular plates made up with a 5" hole in the center of both of them, apparently I had them made up just a bit too big and decided that I would simply 'notch' the ends where they went into the tower vertical supports.
I ended up taking off about 1/4" from each side of the corners, this gives me some extra 'wiggle room' in case I have to move the plates around a little bit so that the collars are in the proper alignment. Here is a shot showing one corner modification: Just in case anything was off I decided to mark the orientation of both of the plates so that I could put them back into the original positions. I used a drill bit and made a divot at one corner of each plate as well as a couple on the matching side of the tower upright. I had a piece of thick wall tubing with the dimensions 4-7/16" ID and 5-1/2" OD, about a 1/2" thick wall. This material I am going to use to make up two collars that will be welded into the center of the plates and the stub pipe of 4-1/2" schedule 80 pipe will go into. I cut two pieces about 6" long each, and using my lathe bored the inside diameter to about .060" over the outside diameter of the 4-1/2" pipe. In addition to boring the ID, I put a rabbit on one end about 1/4" long so that it would fit into the hole in the 3/8" plate, this will help keep things aligned so that I can weld them into position. Once the collars were made up I put them onto the stub pipe and put the pipe into position inside the tower. After wrestling around with the stub pipe (it's over 200lbs! and 14' long) I got it positioned correctly and tack welded the collars onto the 3/8" plate. Then I removed the stub pipe, removed the plates and welded them up, putting welds on the top and bottom side on of the plates over on my welding bench. Here is a picture of one of the mounting plates: ![]() |
||
| Got started on building the boom crane that will go on top of the tower today. I have a little more work to do to get the bottom collar aligned up better with the top one as the 1-1/2" pipe for the crane doesn't slide easily yet. Once fully aligned I will put a vertical piece of flat stock between the collars so that they do not move. So far this is what the boom crane looks like: ![]() |
||
| Finished up making my coil winder today, I made it so that the center was 9/16" wide. I wound up all 12 of the coils with 80 turns of #12 copper wire. It turned out about perfect as I was able to get 6 coils from each 500' spools that I had, with only about 10' extra remaining on each spool - all together not enough to even wind an additional coil - cutting it pretty close here!
So in all each coil used about 1.58 lbs of copper, and very little remained on the spools. To wire up the coils I ended up unwinding the last coil and cutting it, so each coil ended up being about 79 turns. So in all - almost 20 lbs of copper were used to make up the coils! I found a couple of interesting points, one that winding the coils was a bit tougher than I thought, attention had to be paid to tension, winding evenly along with maintaining a rotation count. One other point was that once the coils were removed from the coil winder that they immediately expanded to about 1" thick! |
||
More tower work. The winch for the boom crane came in last night so I decided to get it mounted onto the frame work. It was a little bit tight as I needed the handle for the winch to rotate without hitting anything. The winch is mounted so that the cable it is roughly in the middle of the width, the cable will go up to the top, around 2 sheaves (still have to get yet) and back down to the bottom of the boom.
Next I had been wanting to build a couple of work platforms that will be near the top of the tower, this way when I am up there I am not standing on angled supports and killing my feet. I had found what I believe they call 'grip step', it is 7" deep and perfect for my application. I fabricated some angled mounts out of 1/4" steel, and they bolt onto the tower. Here is a picture showing the platforms, and another with them mounted on the tower, I only needed two of them as the boom crane is going to be mounted on the other side:
The rest of the day was spent making up a bunch of collars that will be needed for the yaw bearing, tower stub, boom and the crane. |
||
Made up the mount for the thrust bearing (throw out bearing), I made it in two parts from some rough stock that I had and got it welded into the top of the stub. Here is a picture of the mount without and with the thrust bearing:
While at it I also welded in the two collars that keep the yaw bearing square on the stub, as well as a stop collar so that when I retract the stub it will have a positive stop. Here is a picture of the top of the stub with the collars welded on: ![]() |
||
| Continued working on the crane today, got it basically all done with all parts pinned using 3/4" stainless steel pins that I made from some bar stock. Each pin has a washer welded onto the back-side and the opposite end drilled out to use a hitch pin for easy disconnects. The vertical support as well as the top bar have a steel loop welded onto them at their balance points to make it easy to raise and lower if needed.
Here is a picture of the completed crane, in all it extends about 60" above the supporting structure which should give me plenty of height to raise the turbine off the tower stub: Here are some close up pictures of the pinned sections: The picture above shows the bottom collar, which allows a 3/4" bar into it which will be used to keep the boom from retracting. In addition a long bar will be used to help rotate the boom so that anything being lowered can be swung safely away from the tower edge. The end of the topmost bar also has a plate welded onto the end to keep the winch from wandering off, most likely I will not leave the electric hoist connected and bring it up only if needed. And yes, I intend to run 110 volt GFCI outlet up to the top of the tower to power the hoist:: I have been doing a lot of thinking about the top of the tower, eventially I will be putting some eye-bolts into the top plate to make it easier to clip safety equipment onto. Right now there just not enough points in which to clip onto and it will give me a big peace of mind. In addition I want to move the hand winch up to the top of the boom crane, right now it is located at the bottom, I have realized that with it in it's current position that it forces me to move around on the tower more than should be necessary. Currently if alone I had to go to the lower platform and crank up the boom crane, then move to the top platform and pin the diagonal brace, then move back to the lower platform and lower the boom crane so that it rested on the bottom collar. And all that moving around had to be done all over again when I wanted to lower the boom crane - too much! I have learned that when at the top of the tower I really want to move as little as possible, and with the winch at the top it all can be done from a single position. |
.
If you find this site useful and would like to support it, you can do so simply by clicking the button below and donating whatever you like.
To donate you can either use your PayPal account or a credit card (using secure authorization). Donations can be for as little as $1.00
| © 2007-2009 Briery Mountain Enterprises, LLC, Creative Commons "Some Rights Reserved" |
Except where otherwise noted, this site is licensed under a Creative Commons License |